Extra Co -- Center for Composite Materials

Consultancy - 1: Design and drawing validation of FRP chemical storage and dosing tanks was conducted as part of the Chlorine Dioxide Dosing System project, which encompassed design, engineering, procurement, execution, and commissioning of storage and transfer systems for tank capacities of 25 m3, 10 m3, 5 m3, and 3 m3, as specified by EXTRACO in accordance of requirement by Chennai Petroluem Corporation Limited (CPCL). The design has been validated and certified by CCM in accordance with the BS EN 13121-3:2016 standard.

Consultancy - 2: This consultancy assignment outlines a robust methodology for designing and validating pultruded FRP hold-down straps, incorporating adaptable material selection and structural customization to enhance operational reliability and performance in practical deployment scenarios.